Manor Gardens Site Update – 16.01.2023 By Katie Pink 16th January 2023 0 comment Uncategorized Excavated foundation Plots 12, 13 & 14 Retaining wall to plot 7 excavated Internal wall blockwork over dpc completed to Plots 19 & 20 Mortar silo base cast Preparation for in road drainage connection Share: