Argyle Works – 03.10.2024
The timber frame is nearly finished, with roof trusses currently being installed, and felt and batten work underway. The project is progressing according to schedule and remains on track for completion in May 2025.
The timber frame is nearly finished, with roof trusses currently being installed, and felt and batten work underway. The project is progressing according to schedule and remains on track for completion in May 2025.
We would like to give a warm welcome to Deborah Greenhill our new Senior Development Project Manager. Deborah comes with a breadth of experience within the Public and Private sectors and working in residential development.
We have an exciting opportunity for a new NED to join our Board – see advert below for more information. Job Vacancies – Aequus Group (aequusdevelopments.co.uk)
We are thrilled to officially announce the appointment of Andrew Johnston as our new Executive Director of Operations! Andrew will be joining us in September, taking over from Derek Quilter, who is retiring. Andrew brings a wealth of experience to Aequus, with a distinguished career in commercial management and...
First energy-efficient homes ready for residents at Manor Gardens in Frenchay | Newsroom (southglos.gov.uk)
Aequus are proud to announce that our already award winning development at Sladebrook Road has received another award – 2024 Michelmores Property Awards – Residential Project of the Year (35 homes and under). Nearly 2 years from completion, it is wonderful to see that this development is still being...
Great progress on site with the sub-structures and ground floor timber frame completed and the super-structure expected to be watertight by the end of July 2024.
We are pleased to formally welcome Sally Higham who officially commences her role as Chair today. Sally who lives in Bath brings a wealth of experience from the commercial and housing sectors. She is currently group chair of the Rooftop Housing Group, advisory committee member for the Growth Impact Fund...
Works are progressing nicely with under slab drainage installed and the left side slab poured yesterday. The works to the rear left wall have started and all the king posts for the retaining wall have been installed.
8 new build 100% affordable flats Works progressing well onsite, piling completed and on programme for July 2025 completion.