The Show Home is now complete with sales launch taking place on 7th & 8th July – Malmains Drive, Bristol (connells.co.uk)

Progress on the rest of the site at week 48 is:

  • 21-23 (affordable) – fascias and soffits installed, valley gutters being formed then felt and battening  
  • 15-18 (sales) – trusses on this afternoon
  • 13 (sales) – brickwork to wall plate ongoing
  • 20 (affordable) – wall-boarding ongoing
  • 3-7 (sales) first lift brickwork ongoing