117 Newbridge Hill – progress report
Progress Update for week 58:
- Floor finishes completed to second floor.
- First two units now ready for snagging
- Decorations nearly complete on first floor
- Gloss painting completed on first floor
- Scaffold erected in stairwell to allow high level boarding and decorations to commence
- Tiling in progress on first floor
- Plastering to ground floor and basement progressing