117 Newbridge Hill – progress report
Progress Update for Week 50:
- Second fix carpentry underway on second floor
- Second fix mechanical nearly complete on second floor
- Plastering remains in progress on first floor
- Decorations started on first floor
- Boarding of walls and ceiling to ground floor in progress
- Install of external retaining walls complete
- New external steps to flat 2 installed
- Boarding to basement walls and ceiling in progress